Expected Gas Sourcing
Norway, LNG (QA,US)
Benefits
Main Driver
Market Demand
Main Driver Explanation
Introduction of pipeline interconnector with capacity to 8 bcm/year will allow to increase technical abilities of gas import by Ukraine from European
countries by 40% (to 29.6 bcm/year). Resolution of the issue of connection of existing pipelines and planned interconnectors of four Vyshegrad States to
the West part of Ukrainian GTS and Ukrainian underground storage facilities makes it possible to create the powerful East-European gas hub. Pipeline
LQWHUFRQQHFWRU ZLOO DOORZ IRU 8NUDLQH WR SXUFKDVH QRW QO\ 5XVVLDQ JDV EXW DOVR JDV WKURXJK WKH /1* WHUPLQDO LQ ĞZLQRXMğFLH IURP 4DWDU WKH 8QLWHG 6WDWHV
etc. and gas from Norway.
PCI Details
PCI Benefits
General Criteria Fulfilled
No
Specific Criteria Fulfilled
Competition, Market Integration, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Drozdovychi - Bilche Volytsya
1,000
110
Total
110
Schedule
Start Date
End Date
Pre-Feasibility
12/2014
Feasibility
12/2014
12/2015
FEED
05/2016
01/2017
Market Test
Permitting
01/2017
12/2017
Supply Contracts
FID
04/2017
Construction
01/2018
11/2019
Commissioning
2019
2019
NDP and PCI Information
Part of NDP
Yes (Ten-Year Network Development Plan
of UTG)
NDP Number
N/A
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Not Applicable
Considered Tariff Regime
Not Applicable
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM