Expected Gas Sourcing
LNG ()
Benefits
Main Driver
Others
Technical Information (LNG)
LNG Facility
FSRU Polish Baltic Sea
Coast
Expected Volume (bcm/y)
9
The project under assessment (considered capacity ranges from 4.5 bcm/y up to 9 bcm/y)
Storage Capacity (m3)
170,000
Ship Size (m3)
170,000
Reloading Ability
No
PCI Details
PCI Benefits
Project aims at fulfilling the infrastructure standard (N-1) rule at regional level in accordance with Article 6(3) of Regulation EU, Project aims at
supplying directly or indirectly at least two Member States
General Criteria Fulfilled
No
Specific Criteria Fulfilled
Competition, Security of Supply, Sustainability
Specific Criteria Fulfilled Comments
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
FEED
Market Test
Permitting
Supply Contracts
FID
Construction
Commissioning
2020
2020
NDP and PCI Information
Part of NDP
No (N/A. This is a new project)
NDP Number
Currently PCI
No
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
Not Relevant
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 451 of 620
Current TYNDP : TYNDP 2017 - Annex A