3rd IP between Portugal and Spain (pipeline Celorico-Spanish border)
General Information
Promoter
REN-Gasodutos, S.A.
Operator
REN - Gasodutos, S.A.
Host Country
Portugal
Status
Planned
Website
Project's URLPublication Approval Status
Approved
Sponsors
REN Gasodutos
100%
TRA-N-283
Project
Pipeline including CS
Non-FID
Update Date
24/05/2016
Advanced
Description
The 3RD Interconnection Point (IP) PORTUGAL-SPAIN is located in the priority corridor North-South in Western Europe, and involves Portugal and
Spain by crossing the border between both Member States. This project will connect both gas systems between Celorico da Beira (Portugal) and
Spanish border, through a pipeline with 162 km of length. This project enables the projects TRA-N- 284 3rd IP between Portugal and Spain
(Compressor Station), TRA-N-285 3rd IP between Portugal and Spain (pipeline Cantanhede-Mangualde) and TRA-N-320 Carregado Compressor
Station.
Regulatory Decisions and
similar material conditions
Enabled Projects
Project Code Project Name
TRA-N-285 3rd IP between Portugal and Spain (pipeline Cantanhede-Mangualde)
TRA-N-284 3rd IP between Portugal and Spain (Compressor Station)
TRA-N-320 Carregado Compressor Station
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
VIP IBERICO
REN - Gasodutos, S.A.
2021
PT
ES
70.0 GWh/d
Comment: First Step of the 3RD Interconnection Point (IP) PORTUGAL-SPAIN.
REN - Gasodutos, S.A.
2021
ES
PT
85.0 GWh/d
Comment: First Step of the 3RD Interconnection Point (IP) PORTUGAL-SPAIN.
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 453 of 620
Current TYNDP : TYNDP 2017 - Annex A