Expected Gas Sourcing

LNG (DZ,NO,QA,US,WO,YE)

Benefits

Main Driver

Market Demand

Main Driver Explanation

Time Schedule

Grant Obtention Date

Delay Since Last TYNDP

3 years

Delay Explanation

Demand forecasts decrease due to the economic and financial context in Portugal and in the EU. Decrease in the demand for the CCGTs due to

the low prices of the CO2 emissions.The investment in this infrastructure should be decided by 2018, with the commissioning to occur by the

end of 2021.The schedule of this project is aligned and is a enabler of the PCI project 5.4 - 3rd interconnection between Portugal and Spain

(TRA-N-283, TRA-N-284, TRA-N-285).

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Setubal - Leiria (Lote 1)

Carregado Compressor Station.

14

Total

14

Schedule

Start Date

End Date

Pre-Feasibility

Feasibility

09/2008

01/2010

FEED

08/2010

11/2010

Market Test

Permitting

02/2011

Supply Contracts

FID

05/2018

Construction

01/2019

12/2021

Commissioning

2021

2021

NDP and PCI Information

Part of NDP

Yes (PDIRGN 2015)

NDP Number

-

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

No

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%