Immingham Storage Co Ltd – Immingham East Terminal - No4 Switchroom Tank Overfill Safety Instrument System

Logic Panel Factory Acceptance Test Procedure

P & I Design Ltd

DOCUMENT NO: SI483005_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 05.03.13

Tel: + 44 (0)1642 617444

PAGE 17 OF 19

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

5.0

CHALLENGE TESTING

Equipment Required

Multi-meter, hand tools, links, yellow highlighter, red pen.

Purpose of Test

To verify the actions of operator interactions do not affect the functionality of the system.

Method Of Test

5.0.1

Verify rising edge action of safety relay reset logic by depressing reset

pushbutton whilst re-establishing level probe connection at incoming terminals

with associated valve closed limit on. Confirm safety relay does not energise

until reset pushbutton released and repressed.

5.0.2

Verify no impact on functionality by repeating import valve loop test

with lamp test pushbutton depressed / linked out. Confirm XSV output actions

correct.

Result

1.

Tank 561 R250.

2.

Tank 564 R330.

3.

Tank 568 R410.

4.

XSV56101.

5.

XSV56401.

6.

XSV56801.

Actions/Comments

Sign

Date

Tested by