Immingham Storage Co Ltd – Immingham East Terminal - No4 Switchroom Tank Overfill Safety Instrument System

Logic Panel Factory Acceptance Test Procedure

P & I Design Ltd

DOCUMENT NO: SI483005_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 05.03.13

Tel: + 44 (0)1642 617444

PAGE 14 OF 19

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

4.2.6 BPCS VALVE COMMANDS

Equipment Required

Multi-meter, hand tools, links, yellow highlighter, red pen, 24Vdc Supply.

Purpose of Test

To verify the functionality of BPCS valve command logic.

To verify the functionality of an open circuit failure.

Method Of Test

4.2.6.1

Connect a 24Vdc supply to incoming terminals. Confirm BPCS valve

command relay energised when 24Vdc supply on and relay de-energised when

24Vdc supply off.

Result

1.

Tank 561 XV56101 R306.

2.

Tank 564 XV56401 R386.

3.

Tank 568 XV56801 R466.

Actions/Comments

Sign

Date

Tested by