Immingham Storage Co Ltd – Immingham East Terminal - No4 Switchroom Tank Overfill Safety Instrument System

Logic Panel Factory Acceptance Test Procedure

P & I Design Ltd

DOCUMENT NO: SI483005_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 05.03.13

Tel: + 44 (0)1642 617444

PAGE 9 OF 19

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

4.2

LOOP TESTING

4.2.1 MANUAL SHUTDOWN – ESD

Equipment Required

Multi-meter, hand tools, links, yellow highlighter, red pen.

Purpose of Test

To verify the functionality of the ESD logic trip and reset actions.

To verify correct lamp status and lamp test action.

To verify the functionality of an ESD fuse failure.

To verify the functionality of an ESD open circuit failure.

Method Of Test

4.2.1.1

Simulate a volt free input to manual shutdowns in the system by

applying and removing a link on the associated incoming terminals.

Input linked manual shutdown relay energised, input open circuit manual

shutdown relay de-energised. Each relay to be tested for energised to de-

energised to simulate external ESD pushbutton action.

4.2.1.2

Open circuit manual shutdown incoming and remote reset link on

incoming terminals, link ESD input confirming relay does not re-energise until

remote reset input is replaced.

4.2.1.3

Remove and replace associated fuse for ESD, confirm ESD relays de-

energised whilst removed.

4.2.1.4

Confirm ESD status lamp illuminated whilst relay de-energised,

extinguished whilst relay energised. confirm ESD status lamp illuminates whist

lamp test pushbutton depressed when relay energised.

Result

1.

ISCo Site ESD R124.

2.

ISCo Site ESD R124A.

Actions/Comments

Approvals (Note: Signature indicates acceptance of test with

actions/comments noted)

Sign

Date

Tested by