Immingham Storage Co Ltd – Immingham East Terminal - No4 Switchroom Tank Overfill Safety Instrument System

Logic Panel Factory Acceptance Test Procedure

P & I Design Ltd

DOCUMENT NO: SI483005_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 05.03.13

Tel: + 44 (0)1642 617444

PAGE 5 OF 19

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

3.0

INSPECTION

3.1

EQUIPMENT CONFORMS TO INSTRUMENT SPECIFICATIONS

Equipment Required

Hand Tools, yellow highlighter, red pen

Purpose of Test

To verify the fitted equipment is as specified.

To verify the fitted equipment is set up as specified.

Method Of Test

Result/Date

3.1.1

Controlled copies of listed specifications will be used to record, by

highlighting (yellow), correct equipment is installed as per Tag number listed on

specification. Errors and omissions will be corrected and noted in red.

Record serial numbers of equipment on controlled copy specifications .

Switches and dials to be adjusted to correct settings as detailed on drawings,

verify set correctly by highlighting (yellow) on controlled copy drawings.

1.

SI277001_SPC - Tank Level Switch (Liquiphant)

Actions/Comments

Sign

Date

Tested by