Immingham Storage Co Ltd – Immingham East Terminal - No4 Switchroom Tank Overfill Safety Instrument System

Logic Panel Factory Acceptance Test Procedure

P & I Design Ltd

DOCUMENT NO: SI483005_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 05.03.13

Tel: + 44 (0)1642 617444

PAGE 4 OF 19

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

2.0

DOCUMENTATION VERIFICATION

Purpose of Test

Verify Correct Documentation used for testing.

Method of Test

Confirm documentation and revisions used for testing.

Record permit number and type (cold/hot/confined space)

Permit To Work Number

Permit To

Work Type

Safety Instrument System Documentation Manual SI483001_MNL Revision

Drawing Number

Title

Revision

SI483005_DWG

SIS Logic Panel External Layout

SI483006_DWG

SIS Logic Panel Internal Layout

SI483007_DWG

SIS Logic Drawing 1 , Power Distribution

SI483008_DWG

SIS Logic Drawing 2 , ESD

SI483009_DWG

SIS Logic Drawing 3 , Tank 561

SI483010_DWG

SIS Logic Drawing 4 , Tank 564

SI483011_DWG

SIS Logic Drawing 5 , Tank 568

Schedules

Title

Revision

SI483003_SCH

No.4 East 500 Series Tanks Safety Functions Matrix

SI483008_SCH

No.5 SIS Logic Panel Label Schedule

Instrument Specifications

Title

Revision

SI277001_SPC

Tank Level Switch (Liquiphant)

Reports

Title

Revision

SI483002_RPT

500 Series Tank Farm Safety Requirement Specification

SI483003_RPT

500 Series Tank Farm Management of Functional Safety

SI483004_RPT

500 Series Safety Instrument System

Actions/Comments

Sign

Date

Tested by