Immingham Storage Co Ltd – Immingham East Terminal - No4 Switchroom Tank Overfill Safety Instrument System
Logic Panel Factory Acceptance Test Procedure
P & I Design Ltd
DOCUMENT NO: SI483005_RPT
2 Reed Street, Thornaby, UK, TS17 7AF
ISSUE: A DATE: 05.03.13
Tel: + 44 (0)1642 617444
PAGE 6 OF 19
Fax: + 44 (0)1642 616447
www.pidesign.co.uk3.2
LOGIC PANEL CONSTRUCTION INSPECTION
Equipment Required
Hand Tools, yellow highlighter, red pen.
Purpose of Test
To verify the logic panel construction is satisfactory to proceed to powered functional testing
.
The logic
panel has been constructed and wired by a competent & reputable panel building company; initial quality
checks have been carried out prior to being available for witnessed factory testing.
Method Of Test
Result/Date
3.2.1
Controlled copies of listed logic drawings will be used to record, by
highlighting (yellow), satisfactory terminations and functions. Errors and
omissions will be corrected and noted in red.
1.
External panel layout and identification conforms to SI483005_DWG and
SI483008_SCH.
2.
Internal panel layout and identification conforms to SI483006_DWG.
3.
Panel physical construction and paintwork satisfactory.
4.
Gland plates correctly fitted and satisfactory.
5.
Doors and locks operational.
6.
Equipment mountings secure.
7.
Panel earthing correct.
8.
All equipment voltage rating correct and conforms to specifications.
Actions/Comments
Sign
Date
Tested by