Immingham Storage Co Ltd – Immingham East Terminal - No4 Switchroom Tank Overfill Safety Instrument System

Logic Panel Factory Acceptance Test Procedure

P & I Design Ltd

DOCUMENT NO: SI483005_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 05.03.13

Tel: + 44 (0)1642 617444

PAGE 10 OF 19

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

4.2.2 MANUAL SHUTDOWN - BUND ISOLATION PUSHBUTTONS

Equipment Required

Multi-meter, hand tools, links, yellow highlighter, red pen.

Purpose of Test

To verify the functionality of the bund isolation pushbutton logic.

To verify correct BPCS interface status.

To verify the functionality of an ESD fuse failure.

To verify the functionality of an ESD open circuit failure.

Method Of Test

4.2.2.1

Simulate a volt free input to each isolation relay in the system. Incoming

terminals linked isolation relay energised, incoming terminals open circuit

isolation relay de-energised. Each relay to be tested for energised to de-energised

to simulate isolation pushbutton action.

4.2.2.2

Confirm BPCS status on outgoing terminals, outgoing terminals to

BPCS closed circuit whilst relay energised, open circuit whilst relay de-

energised.

4.2.2.3

Remove and replace associated fuse for each isolation, confirm isolation

relay de-energised whilst removed.

Result

1.

Tank 561 Isolation R296.

2.

Tank 564 Isolation R376.

3.

Tank 568 Isolation R456.

Actions/Comments

Sign

Date

Tested by