Immingham Storage Co Ltd – Immingham East Terminal - No4 Switchroom Tank Overfill Safety Instrument System

Logic Panel Factory Acceptance Test Procedure

P & I Design Ltd

DOCUMENT NO: SI483005_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 05.03.13

Tel: + 44 (0)1642 617444

PAGE 18 OF 19

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

6.0

ADDITIONAL TESTING

Equipment Required

As required.

Purpose of Test

To verify the actions of additional tests requested by client.

To verify the actions of additional challenge testing as appropriate.

Method Of Test

6.0.1

Detail additional tests carried out.

Result

1.

2.

3.

4.

5.

6.

7.

8.

9.

10.

Actions/Comments

Sign

Date

Tested by