Immingham Storage Co Ltd – Immingham East Terminal - No4 Switchroom Tank Overfill Safety Instrument System
Logic Panel Factory Acceptance Test Procedure
P & I Design Ltd
DOCUMENT NO: SI483005_RPT
2 Reed Street, Thornaby, UK, TS17 7AF
ISSUE: A DATE: 05.03.13
Tel: + 44 (0)1642 617444
PAGE 19 OF 19
Fax: + 44 (0)1642 616447
www.pidesign.co.uk7.0
HANDOVER AND LIFE CYCLE
Equipment Required
None specific.
Purpose of Test
Return logic panel to working condition as found prior to testing.
Update documentation and confirm testing complete to move on to next phase of proof testing.
Method Of Test
7.0.1
Remove all test links and test equipment.
7.0.2
Replace all removable links as found.
7.0.3
Replace incoming and outgoing terminals as found.
7.0.4
Replace or secure covers and guards.
7.0.5
Complete handover and deviation list.
7.0.6
Update documentation as required.
Result
1.
All test links removed.
2.
All removable links as found.
3.
All incoming and outgoing terminals returned to as found.
4.
All covers and guards replaced or secured inside panel.
5.
Handover and deviation list completed.
6.
Documentation update as required.
Actions/Comments
Sign
Date
Tested by