Local Fuel PLC – The Shoreham Oil Terminal

Safety Instrument System Document Verification Procedure LFS-SIS1

P & I Design Ltd

DOCUMENT NO: LF364011_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 20.05.15

Tel: + 44 (0)1642 617444

PAGE 7 OF 7

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

6

DOCUMENTATION VERIFICATION

Purpose of Test

Pre physical on site testing check of documentation to verify correct documentation to be used for testing and

identify modifications to the system since last testing phase.

Incorrect or updated documentation may lead to incomplete testing or undesirable effects on other

site systems and terminal operation.

Controlled Copy Documentation Required

LF364001_REG – LFS-SIS1 Drawing Register

LF364002_REG – LFS-SIS1 Report Register

LF364003_REG – LFS-SIS1 Specification Register

Step

Method of Test

Acceptance Criteria

Pass (

)

Fail (x)

Initial

6.1

Compare system documentation to

registers.

Highlight documentation checked on

controlled copy of registers.

Review changes since last testing phase

as documented in LF364013_RPT -

LFS-SIS1 Operation, Maintenance and

Modification Lifecycle.

Documentation available and auditable.

Documentation revisions reflex installed

system.

Comment any issues in section 6.2 and

review / rectify prior to starting site work

6.2

Comments/Defects/ Remedial Actions

– Report ALL to System Keeper

Tested by

Position

Qualification

Sign

Date

System Keeper Acknowledgement

(Note: Signature confirms System keeper is advised of Comments/Defects/Remedial Actions and will initiate

terminal procedures for rectification works and/or isolation of plant as required)

Accepted by

Position

Qualification

Sign

Date