Local Fuel PLC – The Shoreham Oil Terminal
Safety Instrument System Overfill Shutdown Conditions Proof Testing Procedure LFS-SIS1
P & I Design Ltd
DOCUMENT NO: LF364012_RPT
2 Reed Street, Thornaby, UK, TS17 7AF
ISSUE: A DATE: 20.05.15
Tel: + 44 (0)1642 617444
PAGE 6 OF 22
Fax: + 44 (0)1642 616447
www.pidesign.co.uk5
PREPARATION
All Health and Safety / Permit To Work systems must be implemented before commencing
testing. LF364014_RPT – LFS-SIS1 RAMS is to be submitted for approval prior to the site
testing.
LFS-SIS1 is completely independent of the BPCS, no overrides or special preparations are
required to facilitate uncompromised testing.
Controlled copies of the following documentation will be required:-
LF364012_RPT - LFS-SIS1 Shutdown Conditions Proof Testing (this procedure)
LF364002_SCH - LFS-SIS1 Instrument Schedule
LF364003_SCH - LFS-SIS1 Testing Matrix
LF364011_RPT - LFS-SIS1 Documentation Verification to be completed prior to each
period of testing to confirm correct revisions of documentation.
A controlled copy of this procedure will be used to carry out the testing and will form part of
the lifecycle testing documentation.
Controlled copies of all documentation required for testing to be attached. In addition to
procedures documented in this report calibration certificates, engineers’ reports are to be
issued to each item as applicable.
The functional testing will be controlled and documented by a technician in radio contact
with testers in the switchroom and at field equipment locations as required.