Local Fuel plc - Shoreham Oil Terminal

Safety Instrument System Functional Safety Assessment Stage 5

P & I Design Ltd

DOCUMENT NO: LF364100_RPT

2 Reed Street, Thornaby, UK, TS17 7AF

ISSUE: A DATE: 15.06.2015

Tel: + 44 (0)1642 617444

PAGE 30 OF 32

Fax: + 44 (0)1642 616447

www.pidesign.co.uk

Spurious Trips:

No spurious trips have occurred.

Random Hardware Failure:

No hardware failures have occurred.

Systematic Capability and Systematic Failures:

No systematic failures have been identified.

Operating Difficulties:

Local Fuel plc have taken over the operation of the Terminal and the SIS with no handover

from Valero. They have now operated the system for 18 months and have had no difficulty or

problems with the system.

Interface with BPCS:

The import valve is opened and closed via the HMI system. However, the BPCS can not

interfere with the operation of the SIS system as this is performed on the dedicated hardwired

input to the valve.

The SIS sensors are all displayed on the HMI, but again this is indication only and cannot

interfere with the SIF.

Maintenance Issues:

No issues have been identified.

Functional Capability:

Not included in Revision A of this FSA.

5.8

Training

As stated previously SIS awareness training has been conducted for all operational staff of

Local Fuel plc.

5.9

Further Safety Assessments

Other than for any FSA 5’s due to modification, which will be conducted as and when, it is

not expected to perform a further FSA 4 for approximately three years when Local Fuel plc

will have approximately five years of Terminal ownership and experience in operation of these

systems.

5.10 Compliance to BS EN 61511

Not Included in Revision A of this FSA.