ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects - page 106

SPONSORS
GENERAL INFORMATION
FINANCING
TEN-E Project ?
In PCI list ?
IGAs
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
% Exemption in exit direction
Diameter (range) (inches)
48" or 56"
% Exemption in entry direction
Last completed Phase :
Planned
Diameter (range) (mm)
DN 1200 or 1400
Exemption granted ?
No
Commissioning
2018 Q1
Expected Load Factor
+0.95
Applied for Exemption ?
No
Construction
2017 Q3
Total Compressor Power (MW)
+650.00
Considered Tariff Regime
Negotiated (e.g. Exemption)
FID
2013 Q2
Total Pipeline Length (km)
+1,900
Considered TPA Regime
Negotiated (e.g. Exemption)
End of permitting phase
# of Pipelines, nodes, CS
1
Sponsors are:
Socar (68%), BP
(12%)
and BOTAŞ (15%)
Promoter
Socar
Not part of TEN-E
Public Financing
Operator
TANAP TSO
Yes
Private Financing
TRA-N-221
TANAP - Trans Anatolian Natural Gas Pipeline Project
Non-FID
Pipeline including CS
1
Multilateral Financing
Web Link
Print
ENTSOG TYNDP 2013-2013 - Annex A
Southern Corridor GRIP 2014–2023 Annex B |
106
1...,96,97,98,99,100,101,102,103,104,105 107,108,109,110,111,112,113,114,115,116,...155
Powered by FlippingBook