TRA-N-112
Plinovodi projects cluster 5: R15/1 Lendava - Kidričevo
Non-FID
Pipeline including CS
1
Multilateral Financing
Web Link
2014-2023.pdf
TEN-E Requests
Date of Request
Year Funding Granted
Promoter
Plinovodi d.o.o.
Project of Common Interest
Public Financing
Operator
Plinovodi d.o.o.
Yes
Private Financing
Considered TPA Regime
Regulated
End of permitting phase
# of Pipelines, nodes, CS
1
01.04.2010
Not yet
27.02.2012
Not yet
Applied for Exemption ?
No
Construction
Total Compressor Power (MW)
Considered Tariff Regime
Regulated
FID
Total Pipeline Length (km)
+70.00
% Exemption in entry direction
Last completed Phase :
Planned
Diameter (range) (mm)
DN 500
Exemption granted ?
No
Commissioning
2018
Expected Load Factor
+0.70
% Exemption in exit direction
Diameter (range) (inches)
20"
Print
ENTSOG TYNDP 2013-2013 - Annex A
Southern Corridor GRIP 2014–2023 Annex B |
124
1...,114,115,116,117,118,119,120,121,122,123 125,126,127,128,129,130,131,132,133,134,...155
Powered by FlippingBook