DESCRIPTION OF THE PROJECT
The project is a 29 km gas transmission pipeline connecting the Alexandroupolis LNG import terminal (Project LNG-N-062) to the Greek Natural Gas Transmission System. The pipeline has a 25 km subsea and a 4 km onshore sections.
EXPECTED BENEFITS
Security of Supply, Market integration (SEE+Serbia+FYROM), Diversification of sources, Diversification of routes, N-1 National (Greece), N-1 Regional (SEE+Serbia+FYROM), Back-up for renewables, Power-to-gas.
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
Alexandropolis LNG
268.00
LNG Terminals Greece
Hub Greece
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
ENTSOG TYNDP 2013-2013 - Annex A
Southern Corridor GRIP 2014–2023 Annex B |
69
1...,59,60,61,62,63,64,65,66,67,68 70,71,72,73,74,75,76,77,78,79,...155
Powered by FlippingBook