ENTSOG Southern Corridor (SC) Gas Regional Investment Plan (GRIP) 2014-2023 / Annex B: Infrastructure Projects - page 72

SPONSORS
GENERAL INFORMATION
FINANCING
TEN-E Project ?
In PCI list ?
IGAs
THIRD-PARTY ACCESS REGIME
SCHEDULE
TECHNICAL INFORMATION
Feasibility study to be completed in 2014
% Exemption in exit direction
Diameter (range) (inches)
32"
% Exemption in entry direction
Last completed Phase :
Planned
Diameter (range) (mm)
DN 800
Exemption granted ?
No
Commissioning
2020
Expected Load Factor
Applied for Exemption ?
No
Construction
2015
Total Compressor Power (MW)
# of Pipelines, nodes, CS
3
Considered Tariff Regime
Regulated
FID
Total Pipeline Length (km)
+540
Considered TPA Regime
Regulated
End of permitting phase
TRA-N-068
Ionian Adriatic Pipeline
Non-FID
Pipeline including CS
Promoter
Plinacro Ltd
Web Link
Operator
Plinacro Ltd
Sponsors include (in addition to Plinacro) :
the Albanian Ministry of Economy, Trade and Energy,
the Montenegro Ministry of Economy,
the Bosnia & Herzegovina Ministry of Foreign Trade and Economic Relations
Not part of TEN-E
Public Financing
Yes
Private Financing
2
Multilateral Financing