DESCRIPTION OF THE PROJECT
The interconnection is foreseen to be built as a development to the existing connection of Bulgartransgaz EAD and Botas S.А. – Turkey systems by creating the technical opportunity for enabling bi-directional physical flow of natural gas
between both systems. Thus a significantly greater security of gas supply to Bulgaria can be achieved, meeting the N-1 security standard and diversification of natural gas supply sources.
P
reliminary plans are for a staged project
development.
Currently design activities for the
20 km pipeline section, from CS Lozenets to Nedialsko are underway.
EXPECTED BENEFITS
Security of Supply, Market integration, Reverse Flows, Diversification of sources, Diversification of routes, N-1 National, N-1 Regional (Central and Eastern Europe, South Eastern Europe, Balkan Region), The interconnection Turkey-
Bulgaria is a key project whose realization shall lead to the increase of the security of supply and the opportunity for diversification of gas supply not only to Bulgaria, but to the Central and South-Eastern Europe region as well. The
project contributes directly to the diversification of gas sources: alternative gas producers - countries from the Caspian region, Turkish LNG terminals and Middle East.
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
Interconnector ITB (Turkey - Bulgaria)
92.00
Hub Turkey (Imports)
Hub Bulgaria
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
SOUTHERN CORRIDOR GRIP 2014-2023 - Annex A