Modelled Direction
Yes
exit
Yes
entry
DESCRIPTION OF THE PROJECT
Compressor station extension by 5.7 MW
EXPECTED BENEFITS
Market integration (Increase AT/HU border capacity, Security of Supply of Western Hungary, New power plant supply in Budapest region, Reverse fllow HU>AT, Create capacity RO>AT).
COMMENTS ABOUT THE PROJECT FINANCING
Public financing
Private financing
Multilateral financing
Mosonmagyarovar
153.00
Hub Hungary
Hub Austria
153.00
Hub Austria
Hub Hungary
PROJECTED CAPACITY INCREASES
Interconnection
Capacity (GWh/d)
From Zone
To Zone
ENTSOG TYNDP 2013-2013 - Annex A