Simon Storage, Fluorobenzene Gantry / Tank 24
Instrument & Electrical Installation Tender Package
DOCUMENT REF: SI347001.INS
ISSUE: B DATE: 13.10.97
PAGE: 20 OF 23
4.3.2
Materials
The material prices which the Contractor inserts in the Schedule of Rates shall be deemed
to include the following:-
All costs associated with delivery to the Contractor's site stores or compound.
Any demurrage charges or costs associated with returning packing cases, drums and the
like for materials supplied by the Contractor.
All necessary allowances for waste.
All necessary allowances for consumables.
All necessary fixing devices.
4.3.3
Testing
The man-hour rates shall include for all testing.
4.3.4
Schedule of Day work Rates
Variations shall be valued on a lump sum basis. Such lump sums shall be derived from the
Schedule of Rates below and the man-hour estimates for the variations which the Engineer
has agreed in writing and all of which shall be subject to the issue of a Variation Order.
Position
40 Hour Rate Time & ½ Rate
Double Time
Site Supervision
Working Foreman
Approved Electrician
Instrument Technician
Labourer
Percentage to be added to net cost of materials %
Site Establishment
Cost inclusive of site management, office facilities, £
messing, toilets and constructional equipment at a
weekly rate.