BRAMHALL TERMINAL – BRM-SIS1 ANNUNCIATOR RELAY REPLACEMENT

PHILLIPS 66

16089RPT205B

PAGE 11

6

MANAGEMENT OF CHANGE

6.1 Project Design Change Procedures

6.2 Approvals for the Modification

6.3 Verification and Validation

To ensure verification of the proposed modification through the implementation phase and

validation of the installed modification the following procedure will be utilised.

Project Design Changes

MOC Number 152

Description of Procedure

employed

Management of Change Procedure detailing the following:

Description of the modification, Reason for modification, Identified

hazards during modification, Impact on FS, Design of the

modification, SIS documentation impacted by the modification,

Implementation Plan, Testing Plan, approvals and responsibilities

Does the procedure

satisfy the requirements

Yes No

If No, then detail below what actions are required;

Originator of

modification;

Name - Position

S.Joyce

Maintenance Supervisor

Modification request

approved by;

Name - Position

Name

Position

Responsibility for

design by;

Name - Position

D.B.Faulkner

P&I Design Ltd

Instrument Engineer

Responsibility for

implementation by;

Name - Position

D.B.Faulkner

P&I Design Ltd

Instrument Engineer

Responsibility for

validation by;

Name - Position

D.B.Faulkner

P&I Design Ltd

Instrument Engineer

Management of

Functional Safety

Procedure

MOC Form SHE/PX/M/F/4.11.1

Verification

Procedures to be

utilised for the

modification

MOC Form SHE/PX/M/F/4.11.1

Validation

Procedures to be

utilised for the

modification

MOC Form SHE/PX/M/F/4.11.1