BRAMHALL TERMINAL – BRM-SIS1 ANNUNCIATOR RELAY REPLACEMENT

PHILLIPS 66

16089RPT205B

PAGE 12

7

LIFECYCLE DOCUMENTATION

Considering the proposed modification, it is felt that the modification will require the following

lifecycle documentation to be reviewed and possibly modified:

Hazard and Risk

Analysis

HAZOP

Yes No

Not applicable, no change to hazard

LOPA

Yes No

Not applicable, no change to protection layers

Safety Requirement

Specification

Yes No Not applicable, no changes

Software Requirement

Specification

Yes No Not applicable, hardwired system

FSA Stage 1

Yes No Not required

Design Documentation

Process &

Instrumentation Drawing

Yes No

Not applicable, no plant changes

Schematic overview

Drawing

Yes No

Not applicable, no plant changes

Equipment

Specifications

Yes No

No specific specification, relay type listed on

drawings.

Loop and Hook Up

Diagrams

Yes No

See MOC

Logic and Panel

Drawings

Yes No

See MOC

SIL Verification

Document

Yes No

Not applicable, non SIL rated

Software

Documentation

Yes No

Not applicable, hardwired

Cause & Effect

Matrix

Yes No

Not applicable, unaffected

FSA Stage 2

Yes No Not required