Previous Page  171 / 736 Next Page
Information
Show Menu
Previous Page 171 / 736 Next Page
Page Background

that the appeal was incompetent in that (a) the

word "decision"

in Section 7 did not include

sentence, and that (b) the Law Society was not

a person aggrieved. It was held that the sentence

pronounced by the committee was an operative

part of the decision. The matter was put beyond

all doubt by the terms of the Act which provided

that the committee should set forth in their de

cision, in the case of a conviction particulars of

the conviction and sentence. The Council might

well be a person aggrieved by the decision of the

committee. The legislature had made the Law

Society the'guardian of the public interest so far

as concerned the maintenance of the standard of

the profession of

solicitors. The present peti

tioners

therefore qualified as persons aggrieved

within the meaning of Section 7 of the 1958 Act.

Reference was made

to Attorney General of

Gambia v. N'Tie (1961) AC 617. The fine of

£25 was quite out of proportion to the gravity of

the offence. A censure, even if coupled with a

fine of the maximum sum of £250 would not be

adequate punishment

for

the breach of

rule

established. The Court accordingly ordered that

the respondent should be suspended from prac

tice for a period of five years and reaffirmed the

finding of expenses made against him by

the

Discipline Committee.

(Council of Law Society of Scotland v. Doc-

herty, 112, S.J. p. 312).

Contract—Liability of Builder to re-do work.

The plaintiffs, Builders, contracted with the de

fendants for the conversion of premises into a

shop with upper living accommodation reached

by an outside staircase; the contract contained

provisions for the plaintiff's to provide all mate

rials,

labour and plant

for

the proper and

efficient execution, prosecution and completion

of the works, and to allow for covering up and

protecting the works 'during frosty and inclement

weather or from damage from any other cause

and reinstating any work so damaged', at a price

of some £4,000 for

the whole of

the works

shown or implied on a drawing, to be completed

within a specified number of weeks, payment to

be made in stages on certificates, with a balance

payable on completion 'less 5 per cent, contract

retention for 3 months'. The work inside and

outside the shop (but not the living accommo

dation and staircase) was virtually finished, the

defendants' equipment was inside, the intention

was to open the shop on the following day, and

some £3,250 of the contract price had been paid,

when vandals broke into the shop and did wilful

damage which cost (it was later stated) £450

to make good. At the request of the defendants

the plaintiffs made good

the damage;

they

brought an action for the cost on a quantum

meruit claiming inter alia the existence of a fresh

contract separate from the original by reason of

the request. The defendants contended inter alia

that the original contract was an entire contract

which had not been performed (since the work

had not been completed) and that in order to

fulfil their obligations, the plaintiffs had to make

good the damage even though it was wilful.

Nield J. said that doubt had been thrown on

the extent to which the principle relating to a fresh

contract and quantum meruit applied. His lord

ship, concluded that, in

the circumstances,

in

cluding the allowing of a retention period, the

contract was an entire contract to be completed

before full payment was made. Since the con

tract works were admittedly not completed, the

contract itself was not completed at the

time

when the damage was done; if the obligation on

the plaintiffs to complete the contract involved

doing over again work which had been wilfully

damaged, the harsh liability was one they had to

shoulder. Judgment for the defendants.

(Charon

[Finchley] Ltd. v. Singer Sewing

Machine Co. Ltd. 112. S.J. 536).

Submissions of no case

The Divisional Court of

the High Court

in

England on June 26th said that when faced at

the end of

the prosecution's case with a sub

mission by an accused person there was no case

for him to answer, Justices before passing judg

ment must ascertain whether what was

sub

mitted was part of

the

final speech by

the

accused or whether he made

the submission

while reserving the right to call evidence there

after. Their Lordships allowed an application by

Sheldon, for an order of certiorari to quash his

conviction by Gravesend Justices

in February,

1967, for driving a motor vehicle without due care

and attention, contrary to Section 3(i) of

the

Road Traffic Act, 1960, as amended. No order

as

to costs was made. The Justices did not

appear and were not represented on the appli

cation which was ex parte.

.

The Lord Chief Justice said that the ground

of the application was that the justices had con

victed the applicant on a submission of no case,

whereas he had every intention of calling evidence

if the submission was not upheld. It appeared

that the applicant had in his mind was that in

the event of the submission being rejected, he

29