DOCUMENT NO: SI483005 RPT
ISSUE: A DATE: 05.03.13 -
PAGE 6 OF 19
P
&
I Design
LId
2 Reed Street, Thornaby,
UK, TS17 7AF
Tel:
+
44 (0)1642 617444
Fax:
+
44 (0)1642 616447
www.pidesign.co.uk7.
Panel earthing correct.
6.
Equipment mountings secure.
5.
Doors and locks operational.
4.
Gland plates correctly fitted and satisfactory.
3.
Panel physical construction and paintwork satisfactory.
2.
Internal panel layout and identification conforms to SI483006_DWG.
Controlled copies of listed logic drawings will be used to record, by
highlighting (yellow), satisfactory terminations and functions.
Errors and
omissions will be corrected and noted in red.
3.2
LOGIC PANEL CONSTRUCTION INSPECTION
1.
External panel layout and identification conforms to SI483005_DWG and
./
SI483008 SCH.
Immingham Storage Co Ltd - Immingham East Terminal - No4 Switchroom Tank Overfill
Safety Instrument
System
Logic Panel Factory Acceptance Test Procedure