DOCUMENT NO: SI483005_RPT
ISSUE: A DATE: 05.03.13
PAGE 7 OF 19
P
&
I Design Ltd
2 Reed Street, Thornaby,
UK, TSI7 7AF
Tel:
+
44 (0) 1642617444
Fax:
+
44 (0)1642 616447
www.pidesign.co.uk6.
5.
Termination and crimps tight.
4.
Fuse and
MeB
ratings conform to logic drawings.
3.
Panel wire gauge and colour conforms to panel specification.
2.
Panel wire feruling conforms to logic drawings.
~
1.
Terminals type and numbering conforms to logic drawings.
A random sample of the following tests to be carried out. During the
procedure of functional testing the controlled copies of listed logic drawings will
be used to record, by highlighting (yellow), satisfactory compliance with actions
I to 6.
On completion of all functional testing, all logic drawings should be fully
hi hli hted. Errors and omissions will be corrected and noted in red.
3.3
LOGIC PANEL WIRING INSPECTION
Immingham Storage Co Ltd _ Immingham East Terminal - N04 Switchroom Tank Overfill
Safety Instrument
System
Logic Panel
Factory Acceptance Test Procedure