Previous Page  180 / 336 Next Page
Information
Show Menu
Previous Page 180 / 336 Next Page
Page Background

Recent Irish Cases

Vendor and Purchaser —Deposit forfeited as a

result of delay in completion.

By an agreement of 1 June 1973 between plaintiffs

and defendants, the defendants agreed to purchase

"Brooklawn", Kimmage

Road West, Dublin for

£235,000, of which £23,500 was to be paid as a deposit,

and the balance on completion. The sale was subject

to special conditions and in particular to full planning

permission being granted before 31 December 1973,

the closing to take place within 21 days after that. If

full planning permission was not obtained before the

end of 1973, the period of completion was to be ex-

tended by six months, provided the defendant purcha-

sers agreed to pay initerest at 3% above Bank interest

rate until actual date of completion.

Planning permission was eventually grpnted subject

to conditions on 5 February 1974, and a letter was sent

by plaintiff's solicitor to defendants' solicitors inform-

ing them of this on 8 February, which was acknowledg-

ed on the 11th. On the 12th February, the plaintiffs'

solicitor rashly informed defendants' solicitors that they

wished to have a reply by return. On 8 March the

plaintiff company solicitors informed defendant com-

pany solicitors that the 21 days had expired on 27 Feb-

ruary; they pointed out that at this stage they consider-

ed time to be of the essence of the contract and stated

that they would deem the final closing date to be 15

March. On 13 March, the defendant's solicitors wrote

to plaintiff's solicitors stating that their clients were

entitled to rely on the 6 months extension, and that

time was not of the essence of the contract. On 14

March plaintiff's solicitors reiterated their previous pos-

ition. On 20 March, defendant's solicitors wrote that

they disagreed with this reiteration, but would obtain

client's instructions.

On 10 June, plaintiff's solicitors informed defendant's

solicitors that the time limit for furnishing requisitions

had expired, and asked that the draft deed should be

sent to them for approval; on 12 June, defendant's

solicitors replied that they were obtaining their client's

instructions. On 25 June, plaintiff's solicitors wrote

stating that their clients insisted that the sale be closed

on 1 July. On 27 June, defendant's solicitors rejected

this and stated that a formal notice would be required

if time was to be made the essence of the contract.

As the sale was not closed, on 2 July plaintiff's sol-

icitors said their clients regarded the deposit paid as

forfeited, and would proceed to deal with the property

as owners. On 3 July defendant's solicitors rejected this

contention, and said they would not release the deposit

receipt without client's instructions.

On 5 July, proceedings were instituted by plaintiff

claiming: —

(1) A declaration that it was agreed that the sale

would be closed 21 days after plaintiff obtain-

ing planning permission.

(2) That defendant has persistently refused and

neglected to close the sale, and consequently the

contract is no longer binding.

(3) That plaintiff is fully entitled to deal with the

property and forfeit the deposit.

The Statement of claim was delivered on 31 July. In

the Defence of 18 November, the defendant denies that

full planning permission for building 62 houses had

been obtained, and that time was at any time of the

essence of the contract. The defence alleged that the

plaintiff had wrongfully repudiated the contract. They

made a counterclaim declaration that the agreement

terminated at latest on 30 June, or in the alternative

that it had been discharged by breach of contract.

The plaintiffs submit that they were ready, willing

and anxious to complete at the proper time, and the

Judge accepts this.

It is clear from the correspondance that both parties

or their solicitors interpreted the contract differently.

Th e Court is satisfied that the closing date specified is

21 days after planning permission has been obtained.

However, there was a genuine dispute between the

parties as to interpretation. The conduct of a party is

not necessarily improper because it was based on a mis-

interpretation of the contract, but in this case the delay

by the defendant was not due to any misinterpretation.

The apparent ambiguity with regard to the closing date

was deliberately being used by defendants to delay

completion, even after planning permission had been

obtained. In the circumstances the plaintiffs were fully

justified in serving notice that henceforth time was

deemed to be of the essence of the contract. N o evidence

was adduced by the defendants that there were any

difficulties in the title, or in the preparation of the con-

veyance, or in the raising of the money.

As the contract in this case was not performed, the

plaintiffs are entitled to forfeit the deposit.

Intermational Securities Ltd. v Portmarnock

Estates Ltd.

— Ham i l t on J. — u n r e p o r t ed — 9

Apr i l, 1975.

Order of Mandamus to repair Waterford Court-

house made absolute.

Application to make absolute a conditional order of

Mandamus granted by Finlay, J. in July 1973. That

order commanded the Minister for Justice to exercise

the statutory duties imposed on him by Section 6 (1)

of the Courthouses (Provisions and Maintenance) Act

1935. This Section provides ithat the Minister may di-

rect ithe Commissioners of Public Works to execute such

reports as may be necessary to put the Court accom-

modation in Waterford into proper repair and con-

dition.

176