Interconnection Turkey-Bulgaria
General Information
Promoter
Bulgartransgaz EAD
Operator
Bulgartransgaz EAD
Host Country
Bulgaria
Status
Planned
Website
Project's URL
Publication Approval Status
Approved
Sponsors
Bulgartransgaz EAD for the gas pipeline section
on the territory of Bulgaria
100%
TRA-N-140
Project
Pipeline including CS
Non-FID
Update Date
29/06/2016
Non-Advanced
Description
Construction of new onshore gas pipeline in the section between the village of Losenets and the Bulgarian-Turkish border in the region of the village
of Strandja in parallel to the existing transit gas pipeline of about 76 km length on Bulgarian territory, diameter of the pipe 700 mm and capacity of
about 3 bcm/y at operating pressure 64 bar. A compressor station Losenets – 2 near the existing compressor station in the region of the village of
Losenets is also envisaged to be built. The project, as part of the priority Southern Gas Corridor is crucial in terms of security and diversification of
the sources and routes of natural gas supply to/through Bulgaria and the region. Its implementation is directly related to achievement of the
conditions required for creation of a competitive gas market, increase of systems' flexibility and market integration.
Regulatory Decisions and
similar material conditions
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Interconnector ITB (Turkey - Bulgaria) (BG>TR)
Bulgartransgaz EAD
2020
BGn
BG/ITB
97.0 GWh/d
Interconnector ITB (Turkey - Bulgaria) (TR>BG)
Bulgartransgaz EAD
2020
BG/ITB
BGn
97.0 GWh/d
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 24 of 620
Current TYNDP : TYNDP 2017 - Annex A
Southern Corridor GRIP 2017–2026 Annex B |
18