Previous Page  31 / 56 Next Page
Information
Show Menu
Previous Page 31 / 56 Next Page
Page Background

29

CONSTRUCTION WORLD

OCTOBER

2016

instrumentation construction and mainte-

nance of process plants for Sasol in Secunda

since 2009 and in Sasolburg since 2011.

In comparison to the Sasol Secunda

operation the Sasolburg operation is

certainly smaller, however the division has

been relatively successful in ensuring the

continuity of projects at both locations, here,

in particular within the maintenance sphere.

“Retaining the best core team in the market

is our constant goal,” says August Lipke,

operations director for the division. “Based

on our experience and performance, we have

successfully negotiated a number of E&I

maintenance and construction contracts.”

These include:

• FTWEP Phase 2 (Sasolburg)

• Work pack 01 and 04 E&I (FWSA);

• WP 01/04 Steam Tracing in conjunction

with Stefanutti Stocks Oil & Gas division;

• FTWEP Work Pack 05 & 07 (Linde); and

• DMR (for Worley Parsons) (Sasolburg)

• Medium Voltage and Instrumentation

maintenance (Sasolburg)

• Electrical and Instrumentation

Maintenance (Secunda)

• Plant Light Maintenance (Secunda)

• VOC Expansion Project (Secunda) in

conjunction with Murray & Robberts

• Coal tar Filtration East (Secunda) in

conjunction with Stefanutti Stocks Oil &

Gas division

A recent highlight included the achivement

of a 1,5 million LTIFR milestone by the Stefa-

nutti Stocks’ Electrical & Instrumentation

team that has been undertaking the main-

tenance of Sasol Secunda’s process plant

equipment and plant lights since 2009.

E&I installation

Stefanutti Stocks Electrical and Instrumen-

tation (E&I) annually undertakes multiple

projects for Sasol Synfuels and recently

undertook the E&I revamp of the Sasol’s Poly-

propylene Plant (PP2) unit located in Sasol’s

Secunda complex. The project, entitled the

C3 Expansion Project sees the capacity of the

C3 process equipment increase from 300 ktpa

to 375 ktpa.

The pre-shutdown work included:

• Preparatory work during which

equipment and services were prepared

for the shutdown and changeover.

• The installation of new cableways and

support.

• Pulling in of new cable.

• The installation of new equipment.

• Switching off and removing existing

equipment for refurbishment (typically

drives, instruments and switchgear).

Some of this equipment was refurbished

on site, or in the case of the more

complicated functions, carried out by

Original Equipment (OEM’s) off site.

Shutdown work included the testing, rein-

stallation, reconnection, commissioning and

re-integration of the refurbished equipment

into the operational plant. A total of 200 kilo-

metres of cabling and 140 instruments were

installed during the project.

Specialised grouting

Stefanutti Stocks Civils’ niche capabilities

include foaming agents, cementitious

grouting, epoxy grouting, bentonites, cavity

filling foundation colgrouting and marine

concreting. The division recently undertook

a specialised grouting project for Aveng

Grinaker LTA at Sasol Secunda’s selective

catalytic cracker (SCC) plant.

Epoxy grout was applied to the pump

and compressor bases in the SCC that

outputs ethylene and propylene. This

particular type of grout is utilised in harsh

commercial and industrial applications or in

areas exposed to chemicals. Cementitious

grouting, designed for static or light dynamic

loading (or high temperature exposure), was

applied to all instrumentation baseplates

within the SCC.

Concrete rehabilitation

and repair

Stefanutti Stocks Civils recently completed

the repair to the rim of a cooling tower for

Sasol Synfuels in Secunda. The work area

on top of the 165-metre-high cooling tower

was accessed by means of an Alimak Scando

20/30 construction hoist that was used to

transport all equipment and personnel up to

the top platform. The project scope of work

included the supply, manufacture and instal-

lation of a temporary works platform around

the 206-metre-circumference of the cooling

tower’s top rim.

The repairs (both internal and external to

the spalled concrete) and application of the

polyurethane coating to the rim were under-

taken from the purpose-built circumferential

platform during Sasol’s annual shut down

period of 12 days.

During the project a total of 8 m

3

of

concrete was removed and repaired, 1,1 ton

of reinforcement was replaced and 220 m

2

of

polyurethane coating was applied, following

which all access platforms and hoists

were removed. The project was completed

successfully within the programme’s time-

frame and without any safety incidents.

The group’s oil & gas service offering

extends across the South African borders,

and Stefanutti Stocks Civils KZN recently

completed its fourth project for Sasol Petro-

leum Mozambique Limitada. This entailed

the construction of access roads and five

well pads spread across the Temane and

Inhassoro gas fields, and located over a

50-kilometre distance from the central

processing plant (CPF) in Temane.

“We are proud of our long association

with Sasol, and that we have been able to

offer such a comprehensive skills set to

our client,” says Thompson. “We look for-

ward to continuing to build our relationship

with Sasol, both in South Africa and across

our borders.”

Polyurethane coating is applied to the top rim of

the cooling tower.

A view of the completed access

platforms running around the

circumference of the 165-metres

high cooling tower.

The Alimak hoist being erected along the side

of the cooling tower. This process took about

three weeks with commissioning.