GAZETTE
JULY/AUGUST
1983
Jurisdiction is "to proceed and act and
give relief on principals and rules which in
the opinion of the said Court shall be as
nearly as maybe conformable to the
principals and rules which the Ecclesias-
tical Courts of Ireland have heretofore
acted on and given relief'. The court was
influenced by the fact that the
Ecclesiastical Tribunal had in the cir-
cumstances of this case granted a Church
annulment which was an indication that
canon lawmay embrace not only violence
and threats of violence but also certain
moral pressures of the type evident in this
case.
Held that a decree ofnullity be granted
on the ground of duress, as the will of both
the Petitioner and the Respondent was
overborne by the compulsion of their
respective parents to whom they had been
subject in the parent child relationship and
which drove them to marriage, neither
desired nor gave their consent to.„The
duress exercised was of a nature that they
were constitutionally unable to withstand
nor extract themselves.
M.K. (otherwise M. McC) v. F. McC,
[1982J ILRM 277.
Mary Griffin
CONTRACT —
Agreement to build silent as to a
term, related to services, implied term
should be included in the Agreement.
Council found to be in breach of the
implied term and must compensate for
damage sustained by the Plaintiff.
The Plaintiff a Building Contracting
company claimed damages for alleged
breach of an Implied term of a building
agreement dated 25 July 1974 (the
Principal Agreement) wherein it was
agreed that the Contractors execute and
do all works required in accordance with
the Contract and to the satisfaction of the
council's engineer for the completion of
twenty houses on the Council's site at
Town Parks, Skerries County Dublin.
This site was adjacent to a site owned by
the Plaintiffs on which they also intended
to build forty houses.
A dispute then arose in that necessary
connections for certain services which
were essential for the carrying out of the
works according to the above agreement,
were not provided for or available on the
council's site nor did the agreement
specify the responsibility of either party.
In order to resolve the problem and the
dispute which had arisen between the
parties it was agreed that the Contractors
should secure an agreement, with the
adjacent Developer. Lincoln Develop-
ments Limited whereby this Company
granted the Contractors the saidrights of
connections and services, subject to the
Contractors paying £7,500 to the
Company for,the said rights.
A Supplemental agreement dated 25
May 1976 between the Plaintiffs and the
Council stipulated that the said con-
nections and services were to be provided
from the lands belonging to Lincoln
Development Limited to the Council's
site, and this Supplemental agreement
was to be read in conjunction with the
Principal Agreement and it was agreed in
this Supplemental Agreement that the
council would reimburse the Contractors
the £7,500 paid to Lincoln Developments
Limited and did so.
This dispute resulted in 19 weeks
delay, and the Contractors claimed for
loss and damage which they sustained on
account of this delay on the basis that an
implied term should be read into the
Principal Agreement that there was an
obligation on the part of the Council its
servants, and agents to provide and supply
the said connections and services on the
Council's said site to enable the
Contractors to complete their obligations,
and in failing to do so the Council should
be held liable for loss and damage
sustained.
The Council argued against this:
(a) That the obligations ofproviding such
connections and services could not be
so implied.
(b) That the Plaintiffs were estopped
from claiming damages for delay on
foot of the Supplemental Agreement.
(c) That the delay was due to a difficulty
that arose in regard to the invert levels
at the boundary between the
Council's site and that of Lincoln
Development Limited.
(d) That the Contractors did not need to
negotiate on behalf of the Council
with Lincoln Development Limited,
but for themselves as they were
building forty houses next to the
Council's site.
(e) That when including all precon-
tractual documents and drawings
subsequent to the Principal Agree-
ment the situation shows that the
Contractors were responsible for the
connections and services.
The Court held that neither party con-
sidered or proposed that the Contract
should or could be frustrated. The Court
can imply a term which will implement the
presumed intention, to do what the parties
would have agreed but for their
inadvertent omission.
This power is vested in the Court since
the case of the
Moorcock
[1889] 14 P.D
64. The law looks at what is presumed the
obvious intention ofthe parties, and draws
implications into the Contract with the
object of giving efficacy to the transaction.
The Court held in the instant case that the
course of the conduct of the parties and
the corrspondence indicated that a term or
condition could be read into or implied in
the Principal Agreement, which if it had
been originally included would have
resolved the dispute in issue and further
that the relationship between the parties
was that of employer and contractor and
that the work was carried out on the
employer's site, and if the Contract failed
to provide the necessary term, that the
Council would pay the Contractors the
cost thereof as part of the Contract price.
The court also accepted the statement that
in the ordinary way it's for the
owners/developers of a building site to
provide or obtain the necessary and
essential services for the development.
The Council therefore was in breach of
an implied term of the Principal
Agreement, and were held liable to
compensate the Contractors for damages
suffered by them.
Keegan and Roberts Limited
v.
Comhairle Chontae Atha Cliath.
High
Court (per Ellis J.) — 7 July 1981 —
unreported.
John Gore-Grimes
PLANNING -
Compensation for refusal of Planning
Permission — Undertaking for alter-
native development under Section 57
(3) of Planning Act, 1963 — Validity of
undertaking — Whether claim for com-
pensation is precluded by Undertaking.
The Claimant, applied for outline
Planning Permission for residential
development on 65 acres of his land at
Portmarnock. The Application was
refused by the Respondents and by An
Bord Pleanala, on appeal. The Claimant
then applied for £2.4m. compensation for
such refiisal under Section 55 ofthe Local
Government (Planning and Development)
Act, 1963 (The Act). The claim was
referred to the official Arbitrator. Before
the hearing before the Arbitrator
commenced, the Respondents furnished
to the claimant a document purporting to
be an Undertaking to grant Permission for
a development to which Section 57 of the
Act applied. The Undertaking contained
recitals referring to the claimant's
application and its refusal and the
Respondents proceeded to undertake to
grant permission for the construction of
hotels, theatres or structures for the
purpose of entertainment or any
combination thereof subject to conditions
in relation to. .. (being the matters
specifically mentioned in Section 57(3) of
the Act).
The Respondents submitted that the
delivery of the Undertaking was a
complete answer to the claimant's claim
for compensation. The Official Arbitrator
stated a case for the opinion of the High
Court in which he raised questions as to
whether the Respondents had power to
give a valid Undertaking to grant Planning
Permission in accordance with Section 57
(3) of the Act and, if they had such a
power, whether the Undertaking actually
furnished was valid and had the effect of
xiv