The new Greenfield functions, tested in isolation of
Brownfield, accepted as functioned as designed.
∗
Full function test of Brownfield to Greenfield not
carried out.
∗
New facilities ESD functions were not connected to
the ESD shutdown system.
∗
Result was the ESD functions would never have
worked on demand.
Project 1: Findings