Previous Page  28 / 52 Next Page
Information
Show Menu
Previous Page 28 / 52 Next Page
Page Background

CONSTRUCTION WORLD

FEBRUARY

2017

26

PROJECTS & CONTRACTS

“Our on-site monitoring of the application

involved spot checks on the surface

preparation, as well as Dry Film Thickness

(DFT) readings,” explains Mike Byrd, national

protective coatings specification manager,

Kansai Plascon.

Kansai Plascon had technical specialists

on-site for the project; successfully on

27 November 2015. The Protective Coatings

division has had prior experience with bridge

projects, which stood it in good stead in

clinching the Lesotho contract.

Byrd adds that the success achieved

with this particular project was also due to

Kansai Plascon’s 360° guarantee system,

which involves the end user, applicator and

the coatings manufacturer itself, all backed

up by dedicated aftersales support.

Plascotuff Epoxy MIO Intermediate

Coat is a two-component polyamide epoxy

containing micaceous iron oxide. It provides

a high-build barrier coating for protecting

steel in harsh conditions, and an abrasion-

resistant coat for shop-coated steel.

Plascothane 9000 Polyurethane Acrylic is

a two-component re-coatable polyurethane

acrylic high-performance finish for

maintenance and new construction, with an

excellent decorative appearance. It features

high gloss and colour retention, long term

protection and durability, and is available

in a range of colours. A high DFT can be

achieved with a single application.

The first foundation pour was finished on

30 June 2016 with employees from the

local community working tirelessly through

the days and putting in long hours. The

foundations used extremely low quantities

of Portland cement in the concrete

formulation of its wind turbine foundations.

In fact, these turbine foundations are the

greenest in the country, alongside Khobab

Wind Farm’s sister project, Loeriesfontein

Wind Farm.

Each turbine base has a diameter of

19 metres comprising over 45 tonnes of

reinforced steel. These turbine foundations

are utilising one of the world’s lowest

quantities of Portland cement in the

concrete formulation. Slag, a by-product

from the iron industry, is used to replace

89% of the cement. This has resulted in

what is believed to be, one of the world’s

lowest carbon footprints for any wind farm

foundation. “This revolutionary formula was

tested and successfully implemented by our

sister wind farm, so we were confident from

the onset to use the same formulation,” said

Kevin Foster, project manager for Khobab

Wind Farm.

Situated in the Hantam Municipality,

60 km north of Loeriesfontein in the

Northern Cape, Khobab Wind Farm

employs the majority of its labour from

the Loeriesfontein community, in support

of local employment and upliftment. “We

would like to thank the 100-plus local

workers who have ensured that our project

has continued to forge ahead on time, their

commitment is appreciated,” added Foster.

He continued saying, “As part of our

commitment to skills development and

community development, we have provided

local employees with transferable skills

training, which can be used at other

wind farms or other construction sites”.

The material excavated from the

foundation bases was of a good quality

and was subsequently re-used on site,

specifically for the wind farm road

construction and in the preparation of

the turbine hard stands, situated adjacent

to the foundations.

“In closing, we would like to once again

thank everyone on the construction team,

who worked diligently to complete these

foundations, from batching the concrete to

floating it,” concluded Foster.

The site was chosen because of its

excellent wind resource, its proximity

to national roads for wind turbine

transportation, the favourable construction

conditions, municipality and local

stakeholder support, the straightforward

electrical connection into Eskom’s Helios

substation approximately 11 km south of

the site, and studies showed that there

would be minimum environmental impact.

When operating at full capacity,

the Khobab Wind Farm will generate

approximately 563 500 MWh of clean

renewable energy per year; this is expected

to supply electricity to power up to 120 000

South African homes.

The majority of the 99 m turbine

towers are to be manufactured by GRI, in

Atlantis, in the Western Cape. Civil and

electrical works are to be completed by

a consortium comprised of Murray and

Roberts Construction and Consolidated

Power Projects.

The Khobab Wind Farm is part of the

South African Government’s Round 3

Renewable Energy Independent Power

Producer Procurement Programme

(REIPPP) is expected to be operational

by December 2017.

Wind farm completes foundations on time

Lesotho bridge

project supervision

The project required sand-blasting

the steel bridge surfaces to ISO

8501-1:2007. This was followed

by an application of a zinc-rich

epoxy primer, and two coats each of

Plascotuff Epoxy MIO Intermediate

Coat and Plascothane 9000

Polyurethane Acrylic.

Khobab Wind Farm has announced the completion of its final wind turbine

foundation. All 61 of its wind turbine foundations have been completed

ahead of the schedule, on 5 December 2016.

Mike Byrd, national protective coatings

specification manager, Kansai Plascon.