Previous Page  29 / 52 Next Page
Information
Show Menu
Previous Page 29 / 52 Next Page
Page Background

27

CONSTRUCTION WORLD

FEBRUARY

2017

The R112-million expansion to the select-

services, three-star Metcourt will see a

further 100 rooms added to the popular

hotel. This will boost the hotel from a 248 to

a 348-key facility, extending the capacity of

Emperors Palace to 757 rooms in total.

SMEC South Africa began working on

the project in July 2016, in conjunction

with Boogertman + Partners as principal

architect. “The main challenge is that client

Peermont has already taken bookings for

December 2016, its busiest trading period

of the year. Therefore the project has an

unmovable deadline,” comments lead

structural engineer Brian Seston.

The consulting engineer focused on

completing all of the necessary construction

drawings for main contractor Boutel to begin

the build as fast as possible. Cranage was

erected as of July 2016, with the initial focus

on pile caps, ground beams, and columns.

Seston adds that the piling posed an

initial challenge, as existing services had to

be accommodated. “The slabs are nominally

reinforced concrete slabs, and not post-

tensioned. It is a basic concrete frame

construction,” he elaborates.

The main challenge associated with

the design process has been to match up

seamlessly with the existing structure. “The

aim is for there to be no visible distinction

between the new and old sections, so it

resembles a continuous structure.

“The design was fairly straightforward.

We were locked in by the fact of the existing

structure, which meant we have had to match

all of the slab levels. We had to redesign

some of the ground-floor items in to speed up

the construction process,” he says.

The Metcourt is a contemporary,

functional hotel aimed mainly at business

travellers and convention centre guests.

However, Peermont identified a need to be

able to offer more family-friendly rooms,

and also to cater for large groups travelling

on a budget. The new king and twin-bed

configurations of the rooms offer stay

solutions for a variety of new markets. The

expanded hotel will also feature a single

suite, with its own private balcony.

The 5 166 m

2

extension includes an

addition to the existing F.L.A.G. Café, an

additional lift, enhanced access to the rest

of the complex, a new façade opposite the

Metcourt Suites, and a 24-hour gymnasium.

“While our main appointment is the hotel

extension itself, we are also involved with

some of the smaller works associated

with these extra elements and features,”

Seston concludes.

The wind farms commenced with the

transportation of the various wind turbine

components on 18 April 2016 and have

made great progress with approximately 500

loads successfully delivered to site, before

breaking for the school holiday period.

The projects expects a further 750 loads

to be delivered between 12 January and

September 2017.

The 53 m long wind turbine blades, tower

sections, nacelles and hubs travel on the

N10 via Uitenhage, Graaff-Reinet, Beaufort

West, Three Sisters, and Carnarvon on to

Loeriesfontein. “The blades, towers, hubs

and nacelles are transported a distance of

around 1 158 km and take approximately

three days, travelling at maximum speed

of 50 to 70 km per hour,” explained Kevin

Foster, Project manager for Khobab

Wind Farm.

Transportation is prohibited at night,

during the school holiday period, on public

holidays, during festivals or other special

events. In the towns of Graaff-Reinet and

Beaufort West transportation will be avoided

during peak traffic hours, as far as possible.

The wind farms’ websites include travel

schedules to assist commuters. Foster

continued, “While every effort is made to

minimise traffic disruptions, we urge road

users to exercise extra caution when close

to the abnormal loads and obey all traffic

management instructions; extra care should

be taken if passing the vehicles as the total

length is up to 57,5 m.”

Khobab and Loeriesfontein Wind Farms,

which together span 6 653 hectares, will

produce an impressive combined output

of 280 MW generated by their 122 wind

turbines. This is equivalent of 240 000

average households being powered each

year, providing a massive boost to energy

provision in the country. The site was

chosen because of its excellent wind

resource, its proximity to national roads

for wind turbine transportation and the

favourable construction conditions.

Loeriesfontein progress

Residents of Loeriesfontein and the

surrounding towns of Niewoudtville

and Calvinia will once again be

seeing wind turbine component

sections en route from the Port

of Ngqura, in Port Elizabeth, to

Loeriesfontein Wind Farm and

Khobab Wind Farm.

Nacelle number four is transported to site.

Fastest-track construction project in Gauteng

The Urban Development division of SMEC South Africa was tasked with the

full design of the civil and structural components of the project, followed

by site supervision and project management, function manager – buildings

Marius Mostert explains.

Lead structural engineer, Brian Seston.

Function manager – Buildings,

Marius Mostert.