Previous Page  32 / 52 Next Page
Information
Show Menu
Previous Page 32 / 52 Next Page
Page Background

CONSTRUCTION WORLD

FEBRUARY

2017

30

PROJECT PROFILE

A structurally sound solution came in

the design of a hanging shutter. The critical

load combination for the structure happens

when the water is at its lowest point.

The shutter has been designed to function

normally without the need for water

pressure on the rear face of the unit. The

forces acting on each pedestal connection

on the anchor piles amounted to 665 KN,

requiring the web of the anchor pile to be

stiffened with gussets to prevent buckling.

Horizontal forces which tended to ‘push’

the shutter off the steel piles during casting

were mitigated by pre-welding a cleat to the

king pile prior to driving.

The specification for cope beam

structures to be cast in the dry, called for

clever construction technique in the use

of a de-watered shuttering system. Each

and every pour requires the design and

construction of a new seal to overcome

water and tidal challenges. A double skin

was used to trap water that seeped in

which was then channeled to a sump for

dewatering. Divers are required to tighten

and align the shutter at its base, and then

the pour must be perfectly timed to coincide

with the low tide. This means a fleet of

ready-mix trucks on site, ready to discharge

in order to stay ahead of the tide as it rises.

Stripping of the shutter was only allowed

once the concrete had achieved a minimum

of 35 MPa as the concrete element formed

a cantilever and needed to be able to

support its own weight. Once the concrete

was cast and the shutter stripped, a second

above tidal level cast was undertaken to

bring the quay up to its final level.

Corporate social investment

Ports all over Africa are experiencing high

cargo volumes, calling for greater capacity

to safely accommodate bigger sized ships.

As South Africa’s principal container port

generating more than 60% of revenue, the

Maydon Wharf infrastructure upgrade will

result in much needed increased capacity

for the country’s economic functioning and

growth, and will alleviate the congestion

currently experienced in the port.

The SSA JV team is proud to have

been part and parcel in delivering a key

development project for the client and

ultimately, the contribution to society, it will

make in employment opportunities

in Durban.

Throughout the project duration,

the drive for education and continuous

learning has remained resolute, even with

the economic downturn experienced in

the construction industry. Graduates from

the Go for Gold education to employment

initiative have undergone experiential

training and continue to be part of the

SSA JV team, providing them with the

necessary skills and mentoring for their

professional development.

The project has employed a significant

number people locally, and takes pride

in its commitment towards training and

mentorship, encouraging individuals to

increase their skills set and gain promotion.

In 2014, the SSA JV team were the main

contributors towards the Jirah academy, a

community based satellite campus, which

is now offering N1 to N3 level engineering

studies. The first mainstream engineering

learners graduated in November 2015.

This is an example of how the company’s

investment in educating people impacts the

future of young minds in Wentworth and

extended communities.

Environmental impact

Great care is taken to ensure zero harm to

the little marine life that exists in the port

through efforts in using biodegradable

grease on sheet pile clutches, and

biodegradable shutter oil and foam seals

for the shutters. No major incidents have

occurred to date.

The project has been and continues to

consistently achieve a score between 96

and 99% for the client as well as external

ECO audits. Also, SSA JV have recently

been recertified ISO14001 based on the

Maydon Wharf project. The CSIR does

bi-weekly monitoring during dredging

operations on the berths.

Health and safety

Working over water and in the tidal zone,

with piling various piling activities, diving

operations and heavy plant and machinery

all operating simultaneously in confined

work areas, the health and safety of the

team was an important aspect of the

works. Good working practice and constant

educational topics on safety were part of

the daily preparations on site.

The SSA JV team recently celebrated

1 500 000 LTI free hours in July 2016, a

commendable milestone for a project of

this complexity and nature.