Previous Page  30 / 52 Next Page
Information
Show Menu
Previous Page 30 / 52 Next Page
Page Background

CONSTRUCTION WORLD

FEBRUARY

2017

28

PROJECT PROFILE

Maydon Wharf was developed for the

then expansion of the Durban harbour, in

particular to meet the needs of the growing

Witwatersrand. The berths were built of

timber, with berths 1-4 and 13 and 14 later

rebuilt using steel sheet piles in the 1950s.

Safety is of utmost importance when

dealing with timeworn structures which

have been in use since the mid-1900s.

Constant monitoring of movement of the

existing quay wall is taken very seriously

to prevent collapse or failure during

pile driving, timber pile extraction and

excavations taking place in proximity to

the old berths.

The project is overseen by Transnet

Capital Projects and RCE Consultants are

the design consultants.

Project description

As the largest and busiest shipping terminal

in Southern Africa, the aged berthing

structures require far greater capacity than

the original 20 000 DWT vessels it was

originally designed for to meet current and

future demands.

The reconstruction of Maydon Wharf

consists of demolishing the existing quay

structure, the removal of old timber piles,

installing a new steel combination wall

with concrete cope beam and back of quay

layer works. Included in the scope of works

is the deepening of the seabed by some

4 m to achieve a draft of 14,5 m CD, with

the placement of scour rock adjacent to

the quay wall, preventing washout by the

propellers of the vessels.

Torrential winds and harsh sea

conditions, are just some of the milder

challenges faced on the exciting marine

construction project. At berth 13 and 14,

extremely hard driving conditions were

encountered and the issue was further

exacerbated by the old quay wall alignment

being far worse in condition and envisaged

location, resulting in subsequently changes

in design alignment. As such, all aspects

of the project required exceptional survey

accuracy. Once completed, the six berths

will be able to handle bigger vessels with

drafts of up to 13 metres.

Construction innovation

Two integral elements of the project are

the anchor piling work and concrete cope

beam construction.

A first for South Africa, the Müller

Verpress Pile (MV-Pile or HP) has been

used extensively in Germany, Netherlands

and the United States for anchoring large

combination-wall systems (both grouted

and un-grouted) as an alternative to the

traditional dead man anchor solution and is

known to be exceptionally economical both

in terms of cost and performance. The HP

piling rig makes use of an IHC 70 hydraulic

piling hammer to drive the piles. The barge

is capable of jacking itself out of the water

which prevents it from being affected by the

waves of passing vessels, the swell in the

harbour and also prevents the piling being

affected by tidal variations. By operating

on a hydraulic platform the rig can be

positioned to the millimetre as well as track

to three positions per barge movement.

The bespoke anchor piling barge is

capable of driving the 33 metre long HP

piles, while grout is simultaneously pumped

at 1 000 kPa from a colloidal mixing plant

on land as the pile is being driven. The

grout acts as lubricant during driving and

once set it bonds to the steel pile and

the surrounding substrate increasing the

frictional resistance of the anchor, as well

as protecting it from the adverse effects

of corrosion.

A selection of HP piles are tested

under tension loading of 450 tons on each

berth. The execution of the HP piling can

be measured through the results of the

test piles which have passed the stringent

testing and specification requirements set

forth in the contract. The use of HP piles

something the Stefanutti Stocks Axsys

Joint Venture prides itself in accomplishing

successfully as a first in the country.

The design of a water tight shutter

system for the cope beam construction

was of a complex nature and as such,

required rigorous analysis. Initially, a

detailed concept of a coffer dam was

developed. The coffer dam concept was

however discarded due to handling issues

RECONSTRUCTION

and

DEEPENING

of Maydon Wharf

The Stefanutti Stocks Axsys Joint Venture (SSA JV) was awarded the

contract for the rehabilitation of berths 1-4, 13 and 14 in April 2014,

a total of six out of 15 berths at Maydon Wharf, the Port of Durban’s

largest break bulk, edible oils and dry bulk handling precinct.