CIP Project:

Project Category:

Site:

Description:

Picture/Map:

Justification:

Other

Considerations:

Preliminary Estimate

All projects include in estimate a 25% contingency based on construction cost.

Strategic Goal:

Improved Transportation Mobility

Church Street North Bypass

Transportation

Town Hall Drive at Harris Mill Road extend North to Ferntree Court at New Mason Farm

Provide a future north-south connection to McCrimmon Parkway for Providence Place Subdivision

and other developments on the west side of Church Street between McCrimmon Parkway and NC540.

Area shown in blue.

The Comprehensive Transportation Plan identifies this as a new project. The extension could

potentially connect to Church Street Park, creating a secondary access. Would provide an important

north-south connection in Town to improve mobility in this area.

The land currently belongs to RTP and it is estimated that the Town would need to acquire 29 acres.

There are at least two stream crossings in the area as well as 20-30 foot elevations and topography.

11,362,500

$

Includes: Design, Construction, permits, furnishings