91
CIP Project:
Project Category:
Site:
Description:
Picture/Map:
Justification:
Other Considerations:
Preliminary Estimate
All projects include in estimate a 25% contingency based on construction cost.
Strategic Goal:
Improved Transportation Mobility
Crabtree Hatcher Creek Greenway Loop
Serves the interest of mobility and connectivity. The upated CTP indicates the need for a sidewalk on
both sides of road to be in compliance. A sidewalk segment exists currently on the southwest side of
roadway. This project could also be considered a sidewalk gap projectrather than a greenway
connection.
660,000
$
Includes: ROW, Design and Construction
Bicycle & Pedestrian
FromMorrisville Parkway to the end of Crabtree Crossing Parkway where Crabtree Hatcher
Creek Greenway starts.
Improve greenway connectivity from the Crabtree Hatcher Creek Greenways by extending a multi-use
path about 0.50 miles along Crabtree Crossing fromMorrisville Parkway to current greenway end,
within existing ROW.
This project will improve connectivity and promote non-vehicular transportation as an extension
from the Crabtree Hatcher Creek Greenway. The recent needs assessment survey indicated the top two
desired amenities were walking trails and linked greenways, and is included in the Parks &
Greenways Master Plan. Project could possibly qualify for grant funding through CAMPO or other
transportation related options.