96
CIP Project:
Project Category:
Site:
Description:
Picture/Map:
Justification:
Preliminary Estimate
All projects include in estimate a 25% contingency based on construction cost.
Site has some topography limitations and would require more comprehensive site analysis. It will be
important to consider timing with the renovations at MAFC and loss of tennis courts. The site
additionally complements the recent Crabtree Hatcher Creek Greenway, the recent MCP bathroom
improvements and has historically served as a center piece of the Towns park system. USTA grant
funding potential or other funding sources may assist with court construction.
2,800,000
$
Includes: Design & Construction
Engaged, Inclusive Community
Tennis courts would increase the number of courts available to the public and include lighting to extend
hours available, allowing for instructional programs. Walking trails will provide passive recreation
and exercise opportunities and serve as connectors to adjacent communities. The 2018 Parks and
Recreation Master Plan indicates support for the amenities. The survey report also provides Priority
Investment Ratings for facilities and programs indicate greenway trails are a high priority, along with
fitness opportunities and walking for exercise.
Other
Considerations:
Strategic Goal:
Morrisville Community Park Phase 3
Parks & Recreation
Existing Morrisville Community Park site in the area near the Kudrow Lane parking lot.
The current plan for the park includes construction of tennis courts near the Kudrow Lane parking lot,
walking trails from adjacent communities with connectivity to greenway network, instructional/league
play programs, fitness stations, and miscellaneous site amenities. Additionally, it includes some
existing sports field improvements for ADA compliance, bleachers pads and backstop for T-Ball.