Article 2: Administration

Section 2.5. Application-Specific Review Procedures

2.5.8. Construction Plan Approval

June 23, 2017

Morrisville, NC

Page 2-50

Unified Development Ordinance

2.5.8.

Construction Plan Approval

A.

Applicability

The procedure and standards in this subsection apply to the review of

applications for Construction Plan Approval, which shall be required

before issuance of a Building Permit or Certificate of

Compliance/Occupancy for any development involving grading,

construction of infrastructure and utility improvements, or other land

disturbance. Construction Plan Approval shall also be required before

submittal of an application for Final Plat Approval that includes

infrastructure or utility improvements unless construction and

acceptance of the improvements is ensured by performance and

maintenance guarantees.

An application for Construction Plan Approval shall be submitted and

reviewed concurrently with an application for Stormwater

Management Development Approval. It may be submitted and

reviewed concurrently with an application for Major Site Plan

Approval, Minor Site Plan Approval, Type 1 Subdivision Preliminary

Plat Approval, Type 2 Subdivision Preliminary Plat Approval,

Floodplain Development Permit, Administrative Adjustment, or

Alternative Equivalent Compliance.

(Ord. No. 2016-001, 05/10/2016)

B.

Construction Plan Approval Procedure

Figure

2.5.8.B

and the following subsections identify those steps in the

standard review procedure (se

e Section 2.4)

applicable to the review of a

Construction Plan Approval application and note any specific variations of,

or additions to, those review steps.

Pre-Application Conference

The applicant shall hold a pre-application conference with Town staff

in accordance with Section

2.4.2.

Application Submittal and Acceptance

The application shall be submitted and accepted, and may be withdrawn, in accordance with

Section

2.4.3.

Staff Review and Decision

The Town Engineer shall review the application, allow revisions of the application, and decide the

application in accordance with Section

2.4.4.

The decision shall be one of the following:

a.

Approve the application as submitted;

b.

Approve the application subject to conditions;

c.

Issue a Letter of Conditional Construction Plan Approval; or

d.

Deny the application.

Post-Decision Actions

The post-decision actions and limitations in Section

2.4.8

shall apply to the application except as

follows:

Construction Plan

Approval

Town Council Review and

Decision

Scheduling and Notice of

Meeting

Staff Review and Town

Engineer Decision

Application Submittal and

Acceptance

Pre-Application

Conference

Step is Applicable

Step is Not Applicable

Planning and Zoning

Board Review and

Recommendation

Figure 2.5.8.B