Article 2: Administration

Section 2.5. Application-Specific Review Procedures

2.5.9. Floodplain Development Permit

June 23, 2017

Morrisville, NC

Page 2-52

Unified Development Ordinance

Complies with applicable standards in

Article 5: Development Standards, Article 6: Riparian Buffers, Article 7: Stormwater Management,

and

Article 8: Performance and Maintenance;

Complies with all other applicable standards in this Ordinance;

Complies with the Engineering Design and Construction Manual;

Complies with all other applicable Town ordinances and state and federal laws;

Complies with all requirements and conditions of approval of any prior development permits or

approvals.

2.5.9.

Floodplain Development Permit

A.

Applicability

The procedure and standards in this subsection apply to the review of

applications for a Floodplain Development Permit, which shall be

required before commencement of any development activities within

Floodplain Overlay (FO) districts.

An application for a Floodplain Development Permit may be submitted

and reviewed concurrently with applications for Site Plan Approval,

Construction Plan Approval, or Stormwater Management Permit,

Administrative Adjustment, or Alternative Equivalent Compliance.

B.

Floodplain Development Permit Procedure

Figure

2.5.9.B

and the following subsections identify those steps in the

standard review procedure (se

e Section 2.4)

applicable to the review of a

Floodplain Development Permit application and note any specific variations

of, or additions to, those review steps.

Application Submittal and Acceptance

The application shall be submitted and accepted, and may be

withdrawn, in accordance with Section

2.4.3,

except that the

application shall include certificates of reference level elevations and

any proposed floodproofing. (See

Section 5.6, Floodplain Management.

)

Staff Review and Decision

The Town Engineer shall review the application, allow revisions of the

application, and decide the application in accordance with Section

2.4.4.

The decision shall be one of the following:

a.

Approve the application as submitted;

b.

Approve the application subject to conditions; or

c.

Deny the application.

Post-Decision Actions

The post-decision actions and limitations in Section

2.4.8

shall apply to the application except as

follows:

a.

Effect of Approval

A Floodplain Development Permit allows the approval of any concurrently-reviewed

applications for Site Plan Approval, Construction Plan Approval, Stormwater Management

Permit, Administrative Adjustment, or Alternative Equivalent Compliance for the same

Floodplain

Development Permit

Town Council Review and

Decision

Scheduling and Notice of

Meeting

Staff Review and Town

Engineer Decision

Application Submittal and

Acceptance

Pre-Application

Conference

Step is Applicable

Step is Not Applicable

Planning and Zoning

Board Review and

Recommendation

Figure 2.5.9.B