Morgan Hill, California

137

Zucker Systems

reviewing and approving over-the-counter planning permits (e.g., sign permits,

temporary banners) and building permits (e.g., tenant improvements, small accessory

structures, etc.), administrative use permits, and business license reviews, deposit

processing and application submittals. Generally, the POD’s will handle the TI and

other building permit reviews and the DST handles the business license reviews and

contract planner deposit processing

.

There is a receptionist station to the left of the front counter, where walk-in customers

sign in and are directed to the appropriate staff for assistance. Customers are served in

the order received and their appeared to be adequate chairs and tables for customers to

sit while waiting to be served.

Staff indicated that the Division has not established a policy to serve customers within

15 minutes, which is a standard typically used by best practice communities.

147.

Recommendation:

The Community Development Director should

establish a formal 15-minute wait performance standard Front Counter

customers, which should be tracked in TRAKiT, monitored and reported on

quarterly.

Planning Commission and City Council Approval Processes

The steps involved in the Planning Application Approval process, vary, depending on

the type of application, which determines whether it requires Planning Commission

(PC) and/or City Council (CC) approvals.

Figure 11 below is a flow chart that shows the

general

steps in the existing PC and

CC approval processes. A summary discussion follows.