Morgan Hill, California

142

Zucker Systems

(e.g., have potential impacts that can be mitigated to eliminate impacts) can

be processed by staff or should be outsourced to qualified consultants for

further study and development of appropriate mitigation measures.

154.

Recommendation:

The Community Development Department should

continue to engage qualified environmental consultants to prepare

Environmental Impact Report and/or Environmental Impact Statements for

projects with significant impacts.

12.

Projects are most often found to have no significant impacts or no impacts

with appropriate mitigations and a Negative Declaration (ND) or Mitigated

Negative Declaration (MND) is proposed.

13.

A Notice of Intent (NOI) to adopt an ND or MND is provided for a 20-day

public review and response period, pursuant to state law (e.g., direct mailings,

property posting, newspaper, etc.). If comments on ND or MND are received

the consultant prepares a response. Completion of this step various depending

on number of comments received.

14. Following the 20-day NOI, the project is placed on a Planning Commission

Agenda and a 10-day public hearing notice is provided. The City uses “Notify

Me” software to alert those who have signed up for the service, which is good.

In addition, notices are posted on the City’s website, mailed to surrounding

property owners within 300’, placed in the local newspaper and may also

include property posting. Staff indicated that the 20-day NOI and 10-day

public hearing notice are combined where possible, which is a good practice

that provides interested parties with advance notice of hearings.

See our above recommendation regarding the City assuming the public

notice responsibility as part of the TRAKiT launch to facilitate the online

submittal process.

The assigned project planner uses Legistar software to prepare a draft staff

report. Staff creates a single page cover in Legistar and uploads the staff report

created in MS Word as an attachment to Legistar for PC reports. The report,

PC resolution and Development Agreement DA (when applicable) are written

using templates. Once complete the draft documents are forwarded to the

Director for review and finalization. The Director edits the documents and

finalizes the staff report and staff recommendation. This process, which