Safety Instrument System
Tank Overfill Protection - Management of Functional Safety
P & I Design Ltd
DOCUMENT NO: SI277102_RPT
2 Reed Street, Thornaby, UK, TS17 7AF
ISSUE: B DATE:10.10.12
Tel: + 44 (0)1642 617444
PAGE 11 OF 22
Fax: + 44 (0)1642 616447
www.pidesign.co.uk11.0 INSTALLATION, COMMISSIONING AND VALIDATION
11.1 Pre-Installation
Prior to any installation, the following documentation for the installation, commissioning and
validation are to be produced by P&I Design Ltd. The documentation is as follows:
Title
Document Ref.
SIS Panel Factory Acceptance Test Document
SI277002_RPT
Documentation and Hardware Verification Document
SI277004_RPT
SIS Test Procedure Document
SI277003_RPT
Analysis and Approval Document
SI277009_RPT
Shutdown Conditions Functional Test Document
SI277005_RPT
Process Conditions Functional Test Document
SI277007_RPT
Equipment Failure Testing Document
SI277006_RPT
Roles and Responsibilities:
Immingham Storage Ltd:
Competent person to Review Documents.
Personnel assigned to this phase: From
M.Cook – Environmental & Technical Assistant
C. Newstead – Environmental & Technical Manager
P. Jobling – Group Safety Compliance Manager
A.Dixon - Group SHE officer
A. Rhodes – Terminal Manager
S. Waterman – Terminal Engineer
Any of the above may carry out the checking.
P&I Design Ltd:
Produce Documentation and ensure that they meet the requirements of the SIS Design as well
as the requirements of BS EN 61511.
Personnel assigned to this phase:
Production of Design Documentation
D.S.Regan
Development of Design
P. Potter
Review
P.J.Parkin