Moffat Physical Reverse Flow
General Information
Promoter
National Grid Gas plc
Operator
National Grid Gas plc
Host Country
United Kingdom
Status
Planned
Website
Publication Approval Status
Approved
Sponsors
GNI (UK) Limited
100%
TRA-N-1064
Project
Pipeline including CS
Non-FID
Update Date
23/05/2016
Non-Advanced
Description
Physical Reverse Flow at the Moffat interconnection point, which is currently uni-directional, supporting forward flow only from UK to IE, the Isle of
Man and Northern Ireland (onshore). The planned capacity is 38.5GWH/d
Regulatory Decisions and
similar material conditions
This project is subject to a third party applying to National Grid Gas to connect to the system in accordance with the UK regulatory and commercial
framework. This process may require certain approvals from Ofgem, the UK Regulatory, depending on the nature of the commercial arrangements
(i.e. capacity substitution).
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Moffat
National Grid Gas plc
2020
Y-UKm
UK
38.5 GWh/d
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 568 of 620
Current TYNDP : TYNDP 2017 - Annex A