Gaspipeline Brod - Zenica
General Information
Promoter
BH-Gas d.o.o.
Operator
BH Gas d.o.o.
Host Country
Bosnia Herzegovina
Status
Planned
Website
Publication Approval Status
Approved
Sponsors
BH-Gas d.o.o.
100%
TRA-N-224
Project
Pipeline including CS
Non-FID
Update Date
23/05/2016
Non-Advanced
Description
The starting point of Brod - Zenica gas pipeline is in close vicinity of Brod where it should be connected to the high-pressure gas pipeline
Slobodnica - Brod (TSO ² Plinacro) in the Republic of Croatia. Point of interconnection between Croatian and BiH natural gas transmission network is
Brod/Slavonski Brod. The gas pipeline is planned to be bi-directional, and together with Southern Interconnection BiH/CRO creates a part of EC Gas
Ring.
Regulatory Decisions and
similar material conditions
Capacity Increments Variant For Modelling
Point
Operator
Year
From Gas System To Gas System Capacity
Slobodnica- Bosanski Brod-Zenica
BH Gas d.o.o.
2023
HR
BA
35.0 GWh/d
Comment: Technical exit capacity from Croatia is 44 GWh/day.
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM
Page 580 of 620
Current TYNDP : TYNDP 2017 - Annex A