PCI Details
PCI Benefits
Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation
prior to the commissioning of the project, Project concerns investment in reverse flow capacity
General Criteria Fulfilled
Yes
Specific Criteria Fulfilled
Security of Supply
Specific Criteria Fulfilled Comments
Pipelines and Compressor Stations
Pipeline Section
Pipeline Comment
Diameter (mm) Length (km) Compressor Power (MW)
Castropodame - Zamora
600
170
Guitiriz - Lugo
740
28
Lugo - Villafranca del Bierzo
740
90
Villafranca del Bierzo - Castropodame
740
30
Zamora - La Barbolla - Adradas
800
307
Total
625
Schedule
Start Date
End Date
Pre-Feasibility
Feasibility
FEED
01/2017
05/2018
Market Test
03/2018
Permitting
Supply Contracts
FID
Construction
Commissioning
2025
2025
NDP and PCI Information
Part of NDP
No (The project was not included in the
last NDP that was published in 2008. The
project was identified later on, and was
selected as PCI by the European
Commission in 2013 and in 2015.
Additionally, this project is being
considered in the High Level Group on
Interconnections for South-West Europe. )
NDP Number
Currently PCI
Yes (5.4)
CBCA Decision
No
Market Survey
Not Relevant (no CBCA decision)
Third-Party Access Regime
Considered TPA Regime
Regulated
Considered Tariff Regime
Regulated
Applied for Exemption
No
Exemption Granted
No
Exemption in entry direction
0.00%
Exemption in exit direction
0.00%
Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM