Expected Gas Sourcing

Algeria, LNG (WO)

PCI Details

PCI Benefits

Project changes the capability to transmit gas across the borders of the member states concerned by at least 10%, compared to the situation

prior to the commissioning of the project, Project concerns investment in reverse flow capacity

General Criteria Fulfilled

Yes

Specific Criteria Fulfilled

Competition, Market Integration, Security of Supply, Sustainability

Specific Criteria Fulfilled Comments

Pipelines and Compressor Stations

Pipeline Section

Pipeline Comment

Diameter (mm) Length (km) Compressor Power (MW)

Guitiriz Zamora

It is necessary the increase of the compressor station of

Zamora. This infrastructure should be associated to the third

Interconnection point with Portugal

762

320

16,840

Total

320

16,840

Schedule

Start Date

End Date

Pre-Feasibility

01/2017

Feasibility

01/2017

06/2017

FEED

06/2017

06/2018

Market Test

06/2017

Permitting

06/2017

01/2019

Supply Contracts

01/2019

FID

01/2019

Construction

01/2019

01/2020

Commissioning

2020

2020

NDP and PCI Information

Part of NDP

No (The last approved Spanish NDP ended

in 2016. The Royal Decree-Law 13/2012

cancel the process of obtaining

administrative authorization to transport

pipelines and metering regulation stations

even if they were included in this NDP.This

Project was included in the NDP 2008-

2016.)

NDP Number

N/A

Currently PCI

No

CBCA Decision

No

Market Survey

Not Relevant (no CBCA decision)

Third-Party Access Regime

Considered TPA Regime

Regulated

Considered Tariff Regime

Regulated

Applied for Exemption

No

Exemption Granted

Not Relevant

Exemption in entry direction

0.00%

Exemption in exit direction

0.00%

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 175 of 620

Current TYNDP : TYNDP 2017 - Annex A