Rehabilitation, Modernization and Expansion of the NTS

General Information

Promoter

Bulgartransgaz EAD

Operator

Bulgartransgaz EAD

Host Country

Bulgaria

Status

Planned

Website

Project's URL

Publication Approval Status

Approved

Sponsors

Bulgartransgaz EAD

100%

TRA-N-298

Project

Pipeline including CS

Non-FID

Update Date

22/06/2016

Non-Advanced

Description

A multicomponent project which consists of different actions for rehabilitation, modernization and expansion of the existing gas transmission

infrastructure in Bulgaria and includes activities on: CSs modernization, inspections, repair and replacement of pipeline sections, expansion of the

existing network and implementation of systems for optimization of the management process of the network technical condition. Taking into

account the complex nature of the project, a 3 phases implementation is envisaged: Phase 1: Unifies the actions undertaken in the period 2013-2015,

planned to be finalized in a short term and funded with BTG own resources. Phase 2: Includes actions planned to be initiated in 2016. They represent

logic continuation of the overall realization of the project following the implementation of Phase 1. Phase 3: Conditional infrastructure necessary

after taking the FID for stage 2 of the Interconnection Bulgaria ² Serbia.

Regulatory Decisions and

similar material conditions

Capacity Increments Variant For Modelling

Point

Operator

Year

From Gas System To Gas System Capacity

Interconnector BG RS

IBS Future Operator

2020

BGn

RS

19.4 GWh/d

Comment: infrastructure necessary for stage 2 of the Interconnection Bulgaria ² Serbia.

IBS Future Operator

2020

RS

BGn

19.4 GWh/d

Comment: infrastructure necessary for stage 2 of the Interconnection Bulgaria ² Serbia.

Kulata (BG) / Sidirokastron (GR)

Bulgartransgaz EAD

2020

BGg/BGT

GR

13.8 GWh/d

Strandzha (BG) / Malkoclar (TR)

Bulgartransgaz EAD

2020

BGg/BGT

TRe

58.1 GWh/d

Generated by ENTSOG PDWS on 10/10/2016 05:00:19 PM

Page 29 of 620

Current TYNDP : TYNDP 2017 - Annex A